For the 2,950-metre-long
breakwater, 7 million tonnes of granite stones were deposited in the sea,
placed at depths ranging from 14 to 20 metres. At the base, the stones cover an area of 100 to 120 metres, tapering to
about 10 metres wide at the top. This large triangular wall will serve as a
protective shield for the port.
Construction of the breakwater
began in 2016 and, over the past eight years, has overcome various challenges,
including climate change.
Initially, Cyclone Ockhi caused significant disruptions, destroying part
of the breakwater. Later, a shortage of rocks was resolved by sourcing stones
from quarries in Kerala and Tamil Nadu.
The majority of the breakwater
was constructed between 2021 and 2024. Due to
unfavorable sea conditions during the monsoon, construction was only possible
from October to April each year. In 2022-23, work was halted for 120 days due
to protests by fishermen.
Loading points were established in Kollam and Muthalapozhy to collect
the stones, which were then transported to the placement site via barges.
At Vizhinjam, stones were
gathered at three points…A total of twelve barges were
deployed for the construction.
In the upcoming phase, accropode will be laid around the breakwater to
provide additional protection. A 10-metre-wide concrete road will also be built
on top of the breakwater. Similarly, an additional 900 metres of breakwater
will be constructed in next phase, extending its total length to 3.9
kilometres. No other port in the country
boasts a breakwater of 2.95 kilometres constructed at such depths.