Replying to a
question by Neyyattinkara
MP K Ansalan, Ports Minister GN Vasavan said that while 98% of the dredging and reclamation
work and 81% work on the breakwater has been completed.
The progress of other stages were: berth – 92%,
buildings – 94%, container yard – 74%, project equipment including cranes – 91%
and gate complex and road – 70%.
Last month, Adani
Group, which constructs the port, had informed that all the
technical support systems and experts needed for the operations have been
arranged for the trial run.
To a query on the proposed fish landing centre and
modernisation of the existing fishing harbour, Vasavan said two to three rounds
of discussions were held with port authorities, fisheries department officials
and representatives of trade unions and another round of discussions has been
scheduled on Tuesday and a final decision will be taken on the basis of the
outcome of the talks.