Removal of Baltimore Bridge's Wreckage begins; demolition contractors are at it aiming to finish it faster
Courtesy USCG
Dr.G.R.Balakrishnan Apr 01 2024 Marine News

Removal of Baltimore Bridge's Wreckage begins; demolition contractors are at it aiming to finish it faster

On Saturday, 30 Mar, contractors for the U.S. Army Corps of Engineers began removing the first piece of the wrecked Francis Scott Key Bridge, launching a carefully-planned process to clear a channel and reopen the Port of Baltimore. The work will proceed around the clock, Maryland Gov. Wes Moore said at a press conference Saturday. 

"We'll continue planning efforts for once we open that up for tug and barge traffic to come into the Port of Baltimore," said Coast Guard 5th District Commander Rear Adm. Shannon Gilreath at a press conference Saturday. "Even if it's not the deep draft [channel], we want to take advantage of that opportunity." 

After the debris is cleared, the auxiliary channel will be carefully surveyed to determine draft restrictions…

The alternative arrangements for offloading ro/ro cargo - cars and rolling equipment - are less clear; Baltimore leads the nation in these cargo categories, and only one of its ro/ro terminals is still functioning. "… we don't know the extent of disruption because companies are working on ways to reroute things," said Alliance for Automotive Innovation CEO John Bozzella. 

In the meantime, Port of Baltimore's land-side operations remain open, and longshore workers continue to send import cargo out the gates for final-mile delivery. The port is also exploring other opportunities to bring longshoremen back to work until shipping resumes. 

As the bridge is dismantled, the wreckage will be transported to a scrapping site at nearby Tradepoint Atlantic, Dredging Contractors of America CEO Bill Doyle told The Maritime Executive. He could not give an exact timeline for the work's completion, but said that it would be faster than many observers might think, thanks to an abundance of available private-sector resources. 

Workers at the bridge site have two barge cranes on scene to assist, one rated at 650 tons and one at 330 tons. The East Coast's heaviest crane barge, the Chesapeake 1,000, is standing by to assist when needed. In addition to the resources of the Army Corps of Engineers and its contractors, the U.S. Navy's Supervisor of Diving and Salvage has chartered additional barges to carry wreckage and is mobilizing 12 support vessels to Baltimore, according to Navy Times.

Complex Operation: The cleanup involves cutting and lifting steel debris from the north side of the destroyed bridge. The bridge’s mangled wreckage poses environmental risks, and its removal is essential for restoring navigation and reopening the port. However, this intricate process requires precision and caution according to CoPilot.