“The work on the multimodal cargo
hub at Noida international airport (NIA) is going on in full swing and the
ground filling work is complete. The
foundation work is underway and it will be ready by November,” said Arun Vir
Singh, chief executive officer, NIAL, and the Yamuna Expressway industrial
Development Authority. .
This project spread across 80
acres and being developed by Air India SATS (AISATS) includes integrated cargo
terminal and a warehousing and logistics zone, said officials. “This ambitious
project will offer a transhipment centre and as a warehouse zone for freight
forwarders and integrators. The project will also provide for transportation
facilities to support road-to-road, road-to-air, and air-to-road movements,”
said Singh. Officials said the project
is being developed as per the planned timeline. “Business development
activities are also going on as multiple road shows were completed in May 2024,
targeting international and domestic cargo agents, and airlines. Planned
one-on-one meetings with MNC forwarders, shippers, original equipment
manufacturers, and other stakeholders will take place from this month onwards
for business tie-ups,” said Singh.
Facility tours and engagement
activities are scheduled from September 2024 to March 2025 to familiarise
stakeholders with the facility and ensure smooth collaboration and operations.
Key events and meetings,
including an ORAT (operational readiness and airport transfer) session, customs
and regulatory meetings, and a launch event in December 2024, are also planned
to ensure all operational aspects are addressed.