The
Athikadavu-Avinashi project in Tamil Nadu, which was conceived 67 years ago, is
finally taking shape with Chief Minister M.K. Stalin set to commission the
scheme through video conferencing on Saturday (August 17, 2024).
The project proposes to divert 1.5
thousand million cubic feet (TMC) of surplus water from the downstream of
Kalingarayananicut of the Bhavaniriver at Kalingarayanpalayam in Erode
district, filling 1,045 water bodies and irrigating 24,468 acres of farm land
in Erode, Tiruppur, and Coimbatore districts. The Bhavaniriver originates from
the Nilgiris in the Western Ghats, enters Kerala, and re-enters Athikadavu, a
place near Pilloor dam in Mettupalayam in Coimbatore district. The river enters
the Bhavanisagar dam in Erode district, from where it travels 75 km to join the
Cauvery river at Bhavani.
The
217-km-long perennial river is fed by both southwest and northeast monsoons,
and to utilise the surplus water that enters Cauvery, farmers made a
representation to the then Chief Minister K. Kamaraj in 1957 to divert the
water through open canals and fill the dry pockets in the erstwhile Coimbatore
district.The scheme was initially named the Upper Bhavani Project.
Over the last 50 years, steps were
taken by various State governments to get the scheme up and running. In 2009, a
technical expert committee was constituted under the chairmanship of A.
Mohanakrishnan, Advisor to Government of Water Resources, that investigated the
viability of the scheme. It submitted a
report which stated that 2 tmcft of water during flood flow could be diverted.Political
parties, farmers, traders, welfare organisations, and the public resorted to
various protests over these years urging successive governments to implement
the scheme.
In
1972, the project was re-christened the Athikadavu-Avinashi Ground Water Recharge and Drinking Water Supply Scheme, and the then
Chief Minister Edappadi K. Palaniswami announced the implementation of the
project in 2016-17.The foundation stone for the ₹1,652-crore project was laid
on February 28, 2019, by Mr. Palanisamy, and the project was proposed to be
completed in 34 months. The project cost was revised to ₹1,758.88 crore to fill
32 Public Works Department tanks, 42 union tanks, and 971 ponds in three
districts. After obtaining the environmental clearance, the work for the
project commenced on December 25, 2019.
Delay in acquiring land, obtaining
the right to use permission from farmers for laying pipelines, and the
non-availability of surplus water delayed the project. The trial run was
completed in January 2023 and damages to feeder lines were rectified.The
project was then ready for commissioningProposed
at ₹134 crore during the initial years, the scheme was finally completed at
₹1,916.41 crore. It is executed on a design, built, operate, and transfer
(DBOT) basis, and the contractor, after commissioning, has to operate and
maintain it for 60 months.
On Thursday (August 15, 2024), the
Minister for Housing and Urban Development S. Muthusamy told mediapersons that
adequate water is available for pumping, and that the CM would commission the
project on Saturday.Farmers, social
welfare organisations, and the public, meanwhile, demanded that the government
cover more water bodies under the second phase of the scheme.
D. Prabhu, convenor of Athikadavu-Avinashi Project Struggle Committee,
wanted 1,200 leftover water bodies to be included in the second phase of the
scheme so that it benefits the entire western region of the State. He urged the
government to start work for the second phase at the earliest