“The work on the multimodal
cargo hub at Noida international airport (NIA) is going on in full swing and
the ground filling work is complete. The foundation
work is underway and it will be ready by November,” said Arun Vir Singh, chief
executive officer, NIAL, and the Yamuna Expressway industrial Development
Authority. The project is spread across
80 acres and it is being developed by Air India SATS (AISATS).
NIA had signed an agreement with AISATS for the development of the cargo
hub in February 2024. This project includes integrated cargo terminal and a
warehousing and logistics zone, said officials.
“This ambitious project will offer a transhipment centre and as a
warehouse zone for freight forwarders and integrators. The project will also
provide for transportation facilities to support road-to-road, road-to-air, and
air-to-road movements,” said Singh.
Officials said the project is being developed as per the planned
timeline.
Officials said superstructure works has began this month, focusing on
pardi wall casting and pre-engineered building (PEB) works.
The fitting works, scheduled from August 2024 to October 2024, will
follow the superstructure phase, preparing the facility for operational
purposes.
Recruitment efforts, ongoing
since October 2023, aim to staff the facility appropriately for its operational
needs, said officials. “Business development activities are also going on
as multiple road shows were completed in May 2024, targeting international and
domestic cargo agents, and airlines. Planned
one-on-one meetings with MNC forwarders, shippers, original equipment
manufacturers, and other stakeholders will take place from this month onwards
for business tie-ups,” said Singh.
Facility tours and engagement activities are scheduled from September
2024 to March 2025 to familiarise stakeholders with the facility and ensure
smooth collaboration and operations. Key events and meetings, including an ORAT
(operational readiness and airport transfer) session, customs and regulatory
meetings, and a launch event in December
2024, are also planned to ensure all operational aspects are addressed.