For
the “development of all-weather deepwater 14 million tonne per annum (MTPA)
port at Pavinakurve in Uttara Kannada under the PPP model,” the Karnataka
Maritime Board (KMB) has issued a worldwide tender. Chief Executive Officer Jayaram Raipura of KMB estimates that the
port’s development will cost ₹3,047.86 crore. On the banks of the
Sharavathi and Badagani rivers in Honnavar taluk, along the shore of
Pavinakurve village, is the proposed location for the port’s development.
The Karnataka Public
Procurement Portal offers the project’s tender documents for download.
According to the CEO, 214 hectares of land would be needed to house the port’s
backup area facilities. This land would be generated by reclamation using the
project’s dredged material.
Iron
ore, coal and coking coal, limestone and dolomite, green hydrogen, green
ammonia, liquified natural gas (LNG), and completed steel products were among
the goods that needed to be handled at the port. The port would have deep draft
berthing facilities and state-of-the-art, environmentally friendly high-throughput
equipment to handle cape-sized vessels up to 1,80,000 deadweight tons (DWT). For the aforementioned tender, a pre-bid
meeting has been set for December 10, 2024, using a hybrid format that includes
both a physical meeting in the Office of the CEO, KMB, and a videoconference.
Bids
must be received by January 9, 2025, at the latest. The bidder with the highest
royalty per MT at the planned port would win the project.