Kinet Rail
Solutions, the Indo-Russian joint
venture tasked with manufacturing Vande Bharat sleeper trainsets, has
approached Punjab National Bank (PNB) for a working capital loan of ₹450–500 crore.
The company plans to commence production at its Latur facility in Maharashtra next
year. The loan will be backed by Russia’s Sberbank Rossii, which is acting as
the sovereign guarantor and financier for the project, sources told businessline.
Sberbank is a majority state-owned Russian banking and financial services firm
headquartered in Moscow.
Kinet is a joint venture between India’s Rail Vikas Nigam Ltd (RVNL) with a 25 per cent stake, and Russian
partners Metrowagonmash (70 per cent) and Locomotive Electronic Systems (5 per
cent). The company is responsible for
manufacturing 120 semi-high-speed Vande Bharat trainsets, each with a 16-coach
configuration, under a manufacturing and maintenance contract awarded in
September 2023.
Discussions with PNB began earlier this year to
support working capital needs during the project’s initial phase. This loan is
intended as a bridge arrangement until funding support is cleared by the Railways or
RVNL.
Kinet had earlier sought ₹600 crore in funding from
Russian banks after proposed changes in the train configuration required
additional investments at the Latur facility—such as new sheds and garages.
However, with the Railways deciding to proceed with the original contract
terms, Sberbank has stepped in as the guarantor.
“There is some financing arrangement underway, and
we are told mock-ups (prototypes) are ready,” said a senior Railways official.
The JV has already issued contracts worth ₹450
crore to CG Power for
installation of engines, power systems, and electrical components. Additional
tenders for interior design of the trainsets are expected shortly. Kinet did
not respond to queries from businessline till the time of this
article going to press.
The project
had faced delays due to prolonged discussions over train
configurations. Originally set to produce 120 trainsets of 16 coaches
each, the Railways later proposed an 80 trainset model with a 24-coach design,
requiring substantial redesign and additional investment. Russian partners expressed
reservations about the feasibility of the revised configuration, citing
possible delays.
After extensive correspondence, the Railways
reverted to the original 16-coach plan on February 13, 2025, avoiding immediate
capital expansion at the Latur facility. “The 24-coach configuration required
changes to coach composition, luggage space, pantry areas, and toilets to meet
operational needs. Given the concerns raised, it was agreed to proceed under
existing contract terms,” said a second Railways official. Production is expected to begin once the mock-up receives the necessary
clearances.
The first prototype is likely to be ready by June
2026, after which testing and trial runs will begin, and train-making will
start.